Skip to content
English
  • There are no suggestions because the search field is empty.

📈 CORE KPI: Hitrate

The Hitrate KPI measures how many tasks were completed within the takt as originally planned. It reflects how well operational execution aligns with planning – a key metric in shopfloor management for goal achievement and planning reliability.

🔍 Contents

  • What does the Hitrate show?
  • How is it calculated?
  • Example
  • Aggregation and display across team hierarchy
  • Data sources and system behavior
  • Tips & best practices
  • FAQ


✅ What does the Hitrate show?

The Hitrate shows the percentage of planned tasks that were completed within the defined takt.

  • 100%: All planned tasks were completed within the takt

  • 0%: None of the planned tasks were completed within the takt

  • Low values: May indicate unrealistic planning or capacity bottlenecks


🛠️ How is it calculated?

The calculation happens automatically when the user clicks the “✅ Close takt” button in the Current Takt column (or Current Week).

📐 Formula:

Hitrate (%) = (Completed planned tasks / Total number of planned tasks) × 100

📥 Conditions:

  • The task must already be in the Current Takt column at the beginning of the takt

  • The task must be moved to the Done column during the takt

  • The takt must be actively closed using the “Close takt” button

  • Tasks that were added after the takt began are not included in the calculation


🧾 Example:

At the start of the takt, there are 10 task cards in the Current Takt column.
By the end of the takt, 8 of them are moved to “Done”.

When the takt is closed, the Hitrate is calculated as follows: 

Hitrate = (8 completed tasks / 10 planned tasks) × 100 = 80%

The remaining 2 unfinished tasks stay in the Current Takt column and reduce the overall Hitrate accordingly.


🧩 Aggregation and display across team hierarchy

  • The Hitrate is calculated per team and displayed on the team board under the corresponding KPI tile.

  • In parent teams, an additional KPI “Hitrate aggr.” appears, which shows a weighted aggregation of the Hitrate values from the respective child teams.


🗃️ Data sources and system behavior

  • The KPI uses the system columns “Current Takt” and “Done”

  • Only tasks that were present on the board at the start of the takt are counted

  • The calculation is updated automatically each time the takt is closed

  • Tasks in the Buffer or Next Takt columns are excluded


✨ Tips & Best Practices

  • Close the takt regularly, for example daily or weekly during your team meetings

  • Use the Hitrate to reflect: Was the planning realistic? Are resources missing?

  • Combine the Hitrate with the Disturbance Level KPI to visualize unplanned or spontaneous tasks


❓ FAQ

What counts toward the Hitrate?
→ Only tasks that were in “Current Takt” at the beginning and moved to “Done” before the takt was closed.

What about tasks added during the takt?
→ These are not considered in the Hitrate, but may be reflected in the Disturbance Level KPI.

Are there filters or evaluations by task type?
→ No, the Hitrate KPI does not currently support additional filters or segmentation by task category.